Pinnacle Vastunirman, a developer, has 60 days after obtaining the occupancy certificate to hand over possession, and must give each of 32 buyers ₹20,000 in litigation costs.

Published

Illustration (AI-generated): two tall residential towers with balconies and a few scaffolding sections, behind a paved road in hazy late-afternoon light.Illustration
Illustration (AI-generated): two tall residential towers with balconies and a few scaffolding sections, behind a paved road.

Developer Pinnacle Vastunirman Pvt. Ltd. must pay interest for delayed possession to 32 homebuyers of Pinnacle Neelanchal Phase II in Sus, Pune, under an October 23, 2026 order of the Maharashtra Real Estate Regulatory Authority (MahaRERA).

The builder had cited financial difficulties, disputes with its financier and consent terms signed by certain buyers; MahaRERA rejected those arguments. It held that neither financial difficulties nor disputes with financiers can be used to avoid statutory obligations to homebuyers.

All 32 complainants are to be paid interest from their respective applicable dates until actual possession with an occupancy certificate. The developer must also give each buyer ₹20,000 in litigation costs, ₹6.4 lakh in all.

MahaRERA rejected separate claims for rent reimbursement and compensation for mental agony. The builder has been given 60 days after obtaining the occupancy certificate to hand over possession.

The ruling reinforces homebuyers' rights under Section 18 of the Real Estate (Regulation and Development) Act.