Punawale: Court stays proposed PCMC demolition of 330-sq-metre structure over procedural lapses
A court has ruled that a 24-hour notice alone is insufficient without mandatory safeguards, and has set aside a lower court’s refusal of interim relief to two people.
IllustrationOver procedural lapses, the Ad-hoc District Court has stayed a proposed demolition by the Pimpri Chinchwad Municipal Corporation (PCMC) of a 330-sq-metre structure in Punawale.
The court ruled that a 24-hour notice alone is insufficient without following mandatory safeguards. It observed that PCMC had not submitted evidence of a spot panchnama or dated photographs documenting the alleged unauthorised construction.
The court also set aside the lower court’s refusal to grant interim relief to the two people who had sought it.
Until the civil suit is disposed of, the corporation has been restrained from acting on its February 11, 2026 notice, unless due process is followed. The court clarified that PCMC can initiate fresh proceedings in accordance with the law.