PMC sets November 20 deadline for road excavation on Pune Grand Tour routes, warns of fourfold charges
Contractors who miss set milestones on the Pune Grand Tour road works will be issued show-cause notices, and their contracts could be cancelled if there is no substantial improvement by the next review meeting.
All utility agencies have until November 20 to complete road excavation on the city’s designated cycling routes for the Pune Grand Tour international cycling event, the Pune Municipal Corporation (PMC) has told them. At the joint review meeting on Thursday, Municipal Commissioner Naval Kishore Ram warned that any excavation after the deadline will attract fourfold charges: at least four times the prevailing rates, with no fresh permissions granted.
Ram and Pune District Collector Jitendra Dudi held the meeting to review road, resurfacing, footpath, cycle track and beautification works being carried out in four packages for the event.
The civic administration expressed strong displeasure that utility agencies including Maharashtra Natural Gas Limited (MNGL), Maharashtra State Electricity Distribution Company Limited (MSEDCL), Dinesh Engineering and Allied Digital have not completed excavation within the set timelines despite having permissions. These agencies have been asked to give written undertakings on the work they will finish, the manpower they will deploy and the number of teams they will mobilise.
Show-cause notices will be issued to contractors who miss the set milestones. If progress remains unsatisfactory, penalties will follow under tender conditions, and contracts could be cancelled if there is no substantial improvement by the next review meeting. Completing only the asphalt layer will not count as completing a road stretch.
Ward officers, zonal deputy commissioners and the anti-encroachment department have been directed to remove encroachments, hawkers and other obstructions along the entire cycling route.