PCMC’s Moshi waste-to-energy plant shut for five months; 1.15 lakh tonnes of dry waste pile up
The contractor of the Moshi waste-to-energy plant faces a penalty of ₹50,000 a day from the Pimpri-Chinchwad Municipal Corporation, yet the plant has not resumed operations.
IllustrationSince its chimney collapsed on June 5, 2026, the waste-to-energy plant at the Moshi garbage depot has stayed shut for more than five months, and an estimated 1,15,500 tonnes of dry waste has piled up without being processed.
Civic officials say that, with space for fresh garbage running short, vehicles bringing daily waste to the depot are finding it increasingly difficult to unload.
The plant is operated by Antony Lara Renewable Energy Pvt Ltd. It began working in July 2023 and was designed to burn 700 tonnes of dry waste a day to generate 14 MW of electricity. On July 8, the contractor’s administrative building also collapsed, killing nine employees.
The contractor had assured the civic administration that the chimney would be rebuilt by September 30 and the plant would return to full capacity from October 1. That deadline was missed.
Since October 1, the Pimpri-Chinchwad Municipal Corporation has been imposing a penalty of ₹50,000 a day on the contractor, but the plant has not resumed operations.
Pimpri-Chinchwad generates around 1,579 tonnes of waste every day, of which about 700 tonnes of dry waste was earlier processed at the plant.