MahaRERA order · Business
MahaRERA orders Siddharth Properties to pay interest for delayed possession without OC
MahaRERA ordered interest under Section 18 of RERA from January 1 to March 13, 2023, for the delayed possession of a Pune homebuyer’s flat in the Saarrthi Savvy Homes II project.
IllustrationSiddharth Properties and its promoters must pay a Pune homebuyer interest for a flat in the Saarrthi Savvy Homes II project that was handed over late and without an Occupancy Certificate (OC), MahaRERA has directed.
The authority’s November 3, 2026 order held that a buyer who accepts possession does not lose the right to claim interest for the delay, especially when the flat is handed over without an OC. It ordered interest for the delay from January 1 to March 13, 2023, under Section 18 of RERA.
The buyer booked Flat No. 406 for approximately ₹49.27 lakh plus GST. The agreed possession deadline was December 31, 2022. Possession was actually handed over on March 13, 2023. The project had not received its OC.
Separate claims by the buyer for ₹5 lakh compensation and ₹75,000 legal expenses were rejected.