MahaRERA orders Jairaj Realty to pay buyer interest over Maha Trade Market delay
A Maha Trade Market Phase-1 buyer who booked a commercial unit for ₹50.24 lakh and paid ₹33.39 lakh including taxes alleged being left waiting for possession, and MahaRERA rejected Jairaj Realty's payment-default defence.
IllustrationJairaj Realty LLP must pay delayed-possession interest to a buyer of a commercial unit in its Maha Trade Market Phase-1 project, the Maharashtra Real Estate Regulatory Authority (MahaRERA) has ordered. It held that the developer had failed to deliver possession of Unit B1.012 within the agreed deadline.
The buyer had booked the unit for ₹50.24 lakh through an agreement executed on March 18, 2020. Possession was promised by December 31, 2024, and a six-month grace period extended the deadline to June 30, 2025. MahaRERA held that the occupancy certificate, which is mandatory, was also not delivered within the agreed deadline.
The buyer, who had paid ₹33.39 lakh including taxes, alleged that he was left waiting for possession without any clear construction schedule, even after repeated follow-ups.
Jairaj Realty argued that the buyer had defaulted on payments, claiming nearly ₹7 lakh remained outstanding, and also blamed the COVID-19 pandemic for construction delays. MahaRERA rejected the developer's attempt to blame the delay on alleged payment defaults by the purchaser, observing that the demand notices the developer cited had been issued only after the contractual possession deadline had already expired.
The Authority directed Jairaj Realty to pay interest on the amount received towards the unit cost.