Aundh developer Padmavati Associates hit with ₹12.45 crore NGT penalty

Padmavati Associates must deposit ₹12.45 crore, equal to 10% of the estimated cost of its three projects, with the Maharashtra Pollution Control Board within two months.

Published

Illustration (AI-generated): a cluster of tall apartment towers with construction cranes nearby at a distance in soft evening light, with no peopleIllustration
Illustration (AI-generated): a cluster of tall apartment towers with construction cranes nearby, in soft evening light.

The Western Zone Bench of the National Green Tribunal (NGT) has ordered Aundh-based developer Padmavati Associates to pay ₹12.45 crore as environmental compensation for three projects it built without clearances.

The compensation is ₹12,45,77,156.40 in full. It is for constructing its Pristine Prism, Pristine Royale and Pristine Privilege projects without mandatory environmental clearance, consent to establish or consent to operate.

The penalty is equivalent to 10% of the projects’ estimated cost. It must be deposited with the Maharashtra Pollution Control Board (MPCB) within two months.

The tribunal, hearing a complaint filed by an activist lawyer, also strongly pulled up the State Level Environment Impact Assessment Authority (SEIAA) for failing to initiate action despite knowing about the violations.